BWC MEDGAS / KNOWLEDGE
Knowledge & Resources

Practical technical guidance for planning medical gas installations, selecting components and preparing accurate enquiries.

Installation, Testing & Commissioning

MGPS Handover and Minor Works: A22/A23/A24 Completion and Release Register

Separate system completion, minor-works as-installed information and sectional handover so partially completed wards are never described as fully accepted hospital systems.

AI-generated editorial equipment image: MGPS Handover and Minor Works: A22/A23/A24 Completion and Release Register
MGPS Handover and Minor WorksBWC Medgas · AI-generated equipment illustrationAI-generated editorial equipment image. Illustrative context, not a product specification or project record.

A hospital construction project is frequently delivered in phases: one ward becomes operational while a second level is being fitted out, or new source equipment is connected while parts of the older distribution system remain in service. A single statement that “the MGPS is complete” can be inaccurate, especially when test boundaries and clinical authorization differ across phases.

The 2026 Scottish SHTM 02-01 names Form A22 — MGPS completion certificate, A23 — minor works design review and as-installed information record, and A24 — MGPS sectional completion certificate. These represent valuable distinctions in release scope and documentation.

Distinguish completion from readiness

Mechanical construction may be physically complete without verified gas identification, terminal function, source integration, alarm receiving, defect closure or formal hospital release. Conversely, a tested zone may be properly commissioned even though other areas of the same building remain under construction.

The certificate must say what was accepted and what remains excluded. Avoid language that turns a sectional approval into a whole-hospital statement.

Handover scope register

FieldExact informationWhy it matters
Certificate typeA22, A23, A24 or local approved equivalentDefines document purpose
Service identityOxygen, air, vacuum or other named serviceAvoids vague scope
Physical areaFloors, rooms, zone valves, exact terminal groupEstablishes boundary
As-installed drawingsCurrent approved revisionsMaintenance traceability
Required testsForm numbers and accepted test resultsSupports release
Plant/alarmsRelevant source and receiver dependenciesDemonstrates integration
Open worksExcluded/unfinished sections and safe interfacesPrevents overclaim
DefectsOpen items, accepted dispositions and retestsFormal quality control
AuthorityDesign, installation, verification and hospital signatoriesDecision ownership

A certificate without the attached accepted scope map may be difficult to rely on during later refurbishment.

When minor works are genuinely minor

A23 is not permission to skip a safety assessment. The project should establish what is being changed, which existing drawings are affected, whether loads or service boundaries change, and which reviews and tests are required.

A single added terminal could change the zone, system capacity, permitted future maintenance or the correct as-built branch. The size of the physical fitting is not the whole basis of risk classification.

Example: opening Ward A before Ward B is finished

A hospital intends to occupy Ward A while work continues in Ward B. Both connect to part of a common medical-gas distribution arrangement. The contractor presents a site-wide statement of completion while several shared-area terminal connections are still temporary.

The right record must identify the tested and released Ward A service boundary, any shared dependencies, excluded sections, relevant safeguards and the formal authorized acceptance. Any later change impacting Ward A requires the qualified project's change-control review.

Match the evidence to the exact source

If a source plant is changed during a phased project, earlier terminal tests may need review, and any affected operating conditions or alarms must remain accounted for. The accepted programme should state the dependencies of each sectional completion.

ISO 7396-1:2016 addresses modifications and extensions as well as new installations. Its next edition was under publication as of November 2026; the hospital contract should record its adopted document basis.

As-built records must support future workers

The final information should include service names, route and size details as needed, valve/zone mapping, plant and terminal identities, alarms, test evidence, change dates and responsible personnel.

ISO 11197:2019 is relevant when medical supply units or pendants form part of the installation. A supplier's equipment assembly drawing may need to be integrated with the MGPS as-installed record.

Avoid incomplete handover packages

A pile of unindexed certificates is difficult to audit. Keep a master completion index linking each release boundary to its drawing, test and defect records. Documents should retain version control rather than duplicate filenames with no clear effective revision.

NHS England HTM 02-01 (2026) distinguishes design/validation from operational management; the formal facility authority determines readiness for clinical use.

Commercial closeout and BWC

The procurement contract should specify what manufacturer parts and model information are delivered at handover, including valve boxes, outlets, copper tubes and spares.

BWC Medgas supplies approved components, model documents and product information as agreed; hospital sectional release and testing remain independent responsibilities.

Send the approved replacement or completion component list to BWC Medgas.

Frequently asked questions

Does an A24 sectional completion certificate mean the whole hospital system is finished?

No. Its defined completed section and exclusions control the claim.

Is A23 a waiver of gas-specific testing after minor work?

No. It records the minor-works design/as-installed process; required technical verification is a separate decision.

Primary technical references

CONTACT BWC MEDGAS

Tell us what your project requires.

Share your product list or specifications and we will discuss the options.

WhatsApp